Speeding up MAX reliability improvements

Throughout TriMet, we have been focused on improving MAX on-time performance (OTP) — our measure of reliable service — and doing it safely. Back in January, I shared our plans to improve. We’ve made some progress, and we hope it’s making a difference in your ride. MAX OTP improved from 75 percent last November to an average of just above 85 percent in June. We still have a ways to go, but we are on track and remain dedicated to achieving our long term goal of 90 percent.

rq (4 of 8)

The MAX system is very complex. Over the course of a day, it is in operation for about 22½ hours and provides more than 120,000 trips. It has many moving parts that include 145 vehicles, more than 130 miles of track and overhead wire, more than 250 track switches and nearly 200 rail operators. (And that doesn’t include the many mechanics, cleaners, rail controllers, yard workers, engineers, field operations staff and others who keep our system running safely every day.) There are many events that can cause delays to the system — here’s an update on how we are addressing some of them.

Starting on time, staying on time

To get you where you need to go on time, our trains need to start their day on time. We have improved how we track which trains are ready for service, along with how that is communicated between our maintenance and operations departments. Using the new web-based system speeds up that communication and gives us more time to focus on getting vehicles ready for service safely.

rq (2 of 8)

Our managers, operators and maintenance teams also are working to ensure that our maintenance and operational checks are completed safely and in a timely manner, so our trains depart from the rail yard on schedule. But that’s just the beginning. To stay on time, we’re adding a portable data display to trains that will provide our operators with the current time and the time their train is scheduled to be at the next few stops. These mobile tablets are like the mobile data terminals on our buses that provide operators with key information, such as the time points for where they should be on their routes. I’d like to note that these are important tools to help our rail operators do their jobs, and operators will be instructed on how to use them while safely operating the train.

Uncovering common culprits

We’ve struggled with debris building up in switches, rail joint and track boxes on the Steel Bridge. This has given false indications that the track way on the bridge is occupied when it is not, leading to some significant train delays. The area of issue was in a section of the embedded track where all the MAX lines converge on the west end of the bridge. Crews have now removed the concrete around the track, which has improved drainage and gives our staff better access to keeping debris out of that equipment and also trouble-shooting any electrical issues which can rise from time to time.

Improving the tracks

Our maintenance of way department has been hard at work tackling several track projects. Some have temporarily disrupted MAX service; some have not. On the Red Line, near the Mt Hood Ave Station, crews worked overnight during non-service hours several days in a row last spring, installing anchors to the rail ties. In extreme heat, rails — which are made of steel — can expand and kink, requiring trains to run slower through the area. The new rail ties keep the rail in place. This summer we have experienced several warm days above 80 degrees, where rail temperatures can approach 20 to 30 degrees hotter than the ambient temperatures — so far we have not had any rail movement. This saves approximately 25 to 30 minutes of time throughout each service day, adding back over 150 hours of increased on-time performance over a one-year period.

rq (6 of 8)

During our 1st Avenue MAX Improvements project in May, crews installed new switches and rail and improved the track bed. This disrupted MAX service on 1st Avenue for two weeks, but it has paid off with the removal of slow orders along that stretch of rail.

Now we have another big project approaching fast: From Aug. 21 through Sept. 3, the Rose Quarter MAX Improvements project will replace switches just east of the Rose Quarter MAX Station and redesign the trackway, which will create a smoother ride. We will also upgrade the signal system, which will keep trains running on schedule into and out of the station. Like the work on 1st Avenue, this will require a major disruption to MAX service. Once again, we are asking for your help by adjusting trips to avoid the rush hours, using bus service or other transportation options. Learn more at trimet.org/rosequarter

Thank you for your patience as we continue our work to increase MAX on-time performance. We have much more to do, but we appreciate you staying with us as we keep MAX moving.

Doug Kelsey

Doug Kelsey

As chief operating officer, I oversee our transportation, maintenance and information technology divisions. Outside of work, I enjoy spending time with family and being active outdoors, especially cycling. I’m a huge basketball fan, and I’m proud to be a co-founder of one of Canada’s largest high school tournaments.