As chief operating officer, I oversee our transportation, maintenance and information technology divisions. Outside of work, I enjoy spending time with family and being active outdoors, especially cycling. I'm a huge basketball fan, and I'm proud to be a co-founder of one of Canada's largest high school tournaments.

Speeding up MAX reliability improvements

Throughout TriMet, we have been focused on improving MAX on-time performance (OTP) — our measure of reliable service — and doing it safely. Back in January, I shared our plans to improve. We’ve made some progress, and we hope it’s making a difference in your ride. MAX OTP improved from 75 percent last November to an average of just above 85 percent in June. We still have a ways to go, but we are on track and remain dedicated to achieving our long term goal of 90 percent.

rq (4 of 8)

The MAX system is very complex. Over the course of a day, it is in operation for about 22½ hours and provides more than 120,000 trips. It has many moving parts that include 145 vehicles, more than 130 miles of track and overhead wire, more than 250 track switches and nearly 200 rail operators. (And that doesn’t include the many mechanics, cleaners, rail controllers, yard workers, engineers, field operations staff and others who keep our system running safely every day.) There are many events that can cause delays to the system — here’s an update on how we are addressing some of them.

Starting on time, staying on time

To get you where you need to go on time, our trains need to start their day on time. We have improved how we track which trains are ready for service, along with how that is communicated between our maintenance and operations departments. Using the new web-based system speeds up that communication and gives us more time to focus on getting vehicles ready for service safely.

rq (2 of 8)

Our managers, operators and maintenance teams also are working to ensure that our maintenance and operational checks are completed safely and in a timely manner, so our trains depart from the rail yard on schedule. But that’s just the beginning. To stay on time, we’re adding a portable data display to trains that will provide our operators with the current time and the time their train is scheduled to be at the next few stops. These mobile tablets are like the mobile data terminals on our buses that provide operators with key information, such as the time points for where they should be on their routes. I’d like to note that these are important tools to help our rail operators do their jobs, and operators will be instructed on how to use them while safely operating the train.

Uncovering common culprits

We’ve struggled with debris building up in switches, rail joint and track boxes on the Steel Bridge. This has given false indications that the track way on the bridge is occupied when it is not, leading to some significant train delays. The area of issue was in a section of the embedded track where all the MAX lines converge on the west end of the bridge. Crews have now removed the concrete around the track, which has improved drainage and gives our staff better access to keeping debris out of that equipment and also trouble-shooting any electrical issues which can rise from time to time.

Improving the tracks

Our maintenance of way department has been hard at work tackling several track projects. Some have temporarily disrupted MAX service; some have not. On the Red Line, near the Mt Hood Ave Station, crews worked overnight during non-service hours several days in a row last spring, installing anchors to the rail ties. In extreme heat, rails — which are made of steel — can expand and kink, requiring trains to run slower through the area. The new rail ties keep the rail in place. This summer we have experienced several warm days above 80 degrees, where rail temperatures can approach 20 to 30 degrees hotter than the ambient temperatures — so far we have not had any rail movement. This saves approximately 25 to 30 minutes of time throughout each service day, adding back over 150 hours of increased on-time performance over a one-year period.

rq (6 of 8)

During our 1st Avenue MAX Improvements project in May, crews installed new switches and rail and improved the track bed. This disrupted MAX service on 1st Avenue for two weeks, but it has paid off with the removal of slow orders along that stretch of rail.

Now we have another big project approaching fast: From Aug. 21 through Sept. 3, the Rose Quarter MAX Improvements project will replace switches just east of the Rose Quarter MAX Station and redesign the trackway, which will create a smoother ride. We will also upgrade the signal system, which will keep trains running on schedule into and out of the station. Like the work on 1st Avenue, this will require a major disruption to MAX service. Once again, we are asking for your help by adjusting trips to avoid the rush hours, using bus service or other transportation options. Learn more at trimet.org/rosequarter

Thank you for your patience as we continue our work to increase MAX on-time performance. We have much more to do, but we appreciate you staying with us as we keep MAX moving.

Doug Kelsey

Doug Kelsey

As chief operating officer, I oversee our transportation, maintenance and information technology divisions. Outside of work, I enjoy spending time with family and being active outdoors, especially cycling. I'm a huge basketball fan, and I'm proud to be a co-founder of one of Canada's largest high school tournaments.

More Posts

Making MAX better will take work, time and patience

The oldest section of the MAX Light Rail system has been providing service to TriMet riders for 30 years — and it’s showing its age. So we’re tackling important necessary updates and improvements that will create better — and more reliable — service.

Improving on-time performance

In the past few years, riders have seen MAX delays and disruptions climb. Some of those delays are because of mechanical issues with sections of track called switches, problems with the electronics that operate signals and other complications with elements of the MAX system. As part of our concentrated efforts to improve MAX on-time performance, we will be replacing and upgrading some trackway materials and elements. In addition to making the system more reliable, many of the improvements will allow us to remove precautionary orders where trains run slower in specific areas.

A system well traveled

Before we take a look forward, let’s take a look back. The first section of the MAX system opened on September 5, 1986. Since then:

  • 666.4 million trips have been taken on MAX
  • 73.9 million miles have been traveled by MAX
  • 367,000 miles, on average, are traveled each month by all MAX trains combined
  • 13,000 miles, on average, are traveled each weekday by all MAX trains combined

It is a system well traveled and now it’s time for targeted major replacements and upgrades.

max-improvement-slide (5 of 7)

Taking MAX into the future

The MAX system is made up of track, switches, overhead catenary (power wire) system, traction power substations, signals and communication systems. Upcoming replacements and upgrades will touch all of them. With MAX trains running about 22 ½ hours a day, it is not possible to do all the work necessary in 1½-hour segments. So our focus is to be strategic and lessen the affect on our riders as much as possible. But the projects will affect you and require your patience, understanding and involvement, possibly even altering how and when you ride. The improvements will lead to MAX disruptions — some service impacts may be a day, others a few weeks in duration.

Here’s a look at some of the major work being planned to make MAX better:

1st Ave MAX Improvements (May 8–21, 2016)

The 1st Ave MAX improvements combine three projects into one. Crews will replace switches — sections of track that allow trains to move from one set of tracks to another — on 1st Avenue near SW Morrison and near NW Couch. They’ll replace wooden ties and other elements under and next to those tracks with updated, longer-lasting materials. At the same time, crews will replace rail in the Skidmore Fountain area. Rails wear over time and this section along 1st Avenue is part of the original MAX alignment in use for three decades. The construction will make it necessary to adjust MAX service, including reducing the number of trains running on the system. We’ll be talking more in the coming weeks about how this will affect your MAX trips during the project.

Rose Quarter TC Improvements (Aug. 21–Sept. 3, 2016)

Later this year, work moves to another of the oldest sections of the MAX system — the Rose Quarter Transit Center area. We’ll be replacing switches as well as realigning the track just east of the transit center, which will require moving poles that hold up the overhead power wire and replacing the signal system, among other work. As with the 1st Ave MAX Improvements, MAX service will need to be adjusted during this project.

SW 11th Ave/Steel Bridge Improvements (2017)

Coming in 2017, we expect two more big projects. During one, crews will replace switches, install new rail and reconstruct the track bed at SW 11th Avenue in Downtown Portland, where the original MAX alignment ended. In a separate project, we expect to begin making improvements to switches, signals and the track across the Steel Bridge.

There are other projects in the works, such as:

  • A four-year replacement of overhead power contact wire from Cleveland Ave in Gresham to Lloyd Center.
  • Upgrade and repair platform areas at Gresham City Hall and Washington Park stations.
  • A multi-year effort to design and upgrade the oldest elevators on the MAX system.

We have an aging system and we have work to do to take MAX into the future. It won’t be easy and we’ll be asking for your patience and understanding during the projects, but the projects will improve the system and your ride.

What we’ve already accomplished

Our Maintenance of Way crews are always busy performing maintenance and improvement projects. Here’s a few recent projects completed:

Doug Kelsey

Doug Kelsey

As chief operating officer, I oversee our transportation, maintenance and information technology divisions. Outside of work, I enjoy spending time with family and being active outdoors, especially cycling. I'm a huge basketball fan, and I'm proud to be a co-founder of one of Canada's largest high school tournaments.

More Posts

Here’s How We Plan to Improve MAX Reliability

In the two months since I joined TriMet as the new chief operating officer, I’ve developed an initial focus: delivering more reliable service, and doing it safely.

We know that MAX on-time performance (OTP), our measure of reliability, isn’t what it should be. Right now about one in every five trips is delayed. I know how frustrating this can be, and the impact it can have on a busy schedule. There are places you need to be — work, school, your child’s daycare, the doctor’s office — and it’s our responsibility to help get you there on time.

People took about 38 million trips on MAX last year.

The bottom line is that we need to do better, and earn your trust.

Our teams are working hard to chart a new course. We’re planning to address many areas that affect our system’s OTP, with a goal of raising it over time to an average of 90 percent. (For reference, we averaged 75 percent OTP for MAX in November.)

Achieving this will require some long-term efforts and investments, but I think we can do a lot in the months ahead.

What causes delays?

MAX is a very complex system that operates about 22½ hours a day, with a fleet of 145 vehicles. We’ve looked closely at what causes delays and found that one-third of it revolves around issues like cars blocking the tracks or passengers in need of medical attention — events beyond our immediate control. Even a fallen tree can cause a significant disruption, as we saw in December when it took four hours to clear a tree from the tracks in Downtown Portland. (Even though I was on a bus, we were gridlocked in the traffic backup and I felt the frustration.)

MAX vehicles at Ruby Junction. MAX is a complex system, running 22½ hours a day.
MAX vehicles at Ruby Junction. MAX is a complex system operating 22½ hours a day.

The remaining two-thirds of delays fall within our control, involving trains, signals, switches or numerous other operating issues.

How we’ll improve

To start, we’re focusing on four key areas:

Physical improvements

Parts of the MAX system are 30 years old, and some of its elements need to be upgraded or replaced.

This year, we’re dedicating more than $11 million initially to replace track and switches at the Rose Quarter and along First Avenue in Downtown Portland. (This will also likely require future investments.) Another focus will be on the Steel Bridge, the 104-year-old span that carries four MAX lines over the Willamette. That, along with the adjoining Rose Quarter area, is the site of frequent switch and signal problems. We’re designing an upgrade to the tracks, signals and switches on the bridge, and construction is scheduled to begin in 2017. Given the complexity of the system on the bridge, we’ve hired outside expertise to help us improve reliability and maximize capacity.

Four MAX lines cross the 104-year-old Steel Bridge.
Four MAX lines cross the 104-year-old Steel Bridge.

That’s the good news. However, as you might have guessed, work at the Rose Quarter and along First Avenue is going to require a disruption to MAX service while parts are upgraded or replaced. We’re working on a plan to help keep your ride as smooth as possible during that time, and we’ll share more as we get closer.

Meanwhile, we’ll continue overhauling and upgrading MAX vehicles, making them more reliable for many years and millions of miles to come.

More support for frontline employees

Our ever-growing bus and MAX system means we have a lot of new operators. They’re all capable and professional but, like at any new job, it can take time to get comfortable with the rhythm and intricacies of driving a train on a busy and recently expanded system. That’s why we’re planning to expand our support, coaching and training for operators, helping them become more assured and confident. This should make everyone’s ride smoother and more reliable.

Changing the way we operate

We can also change the way we operate to improve OTP and give you a more reliable ride. We’re working on that now, and I’m excited to see what we come up with. Rest assured, we will never compromise safety.

Working with partners to limit delays

The incident with the fallen tree and the four-hour delay spurred us to meet with the City of Portland to look for ways to shorten delays. We’re also reaching out to our first-responder partners to get trains moving quicker after an incident.

That’s where we start. As this work goes on, I want to be open with you about how we’re doing, the progress we’ve made and what we’ve learned. As I mentioned, this is a complex system and improving it involves focus and resolve. We have a great team of talented and proud people who work very hard to serve you each and every day. We’ll be providing updates and putting together a web page where you can track our performance over time, and we expect to see the number of delays go down over time as our reliability improves.

Doug Kelsey

Doug Kelsey

As chief operating officer, I oversee our transportation, maintenance and information technology divisions. Outside of work, I enjoy spending time with family and being active outdoors, especially cycling. I'm a huge basketball fan, and I'm proud to be a co-founder of one of Canada's largest high school tournaments.

More Posts