The Plan for Morrison-Yamhill

Spring is finally here and we’ll be digging in once again to make major improvements to sections of the original MAX tracks in Downtown Portland.

Like the projects we completed last year at 1st Avenue and Rose Quarter, the Morrison-Yamhill MAX Improvements project will impact service on all lines. But once they’re completed, these track and switch improvements will help us keep trains rolling smoothly and reliably.

The work will take three weeks, from April 30 through May 20. That’s a bit longer than the previous projects that took just two weeks each. The construction will temporarily alter Portland Streetcar in addition to disrupting MAX.

The heart of the project happens on SW Morrison and Yamhill streets at 11th Avenue, which was the end of the original MAX line between Portland and Gresham. This area sees it all: hundreds of trains and streetcars a day, three lanes of auto traffic, bicyclists and pedestrians.

SW 11th Avenue in the early 1980s.

Crews will replace four “turnouts” — two on Morrison Street and two on Yamhill Street. These are sections of track where rails spur off from the mainline to side tracks. Underneath the rails, crews will remove the old wooden ties that were standard at the time of original construction and replace them with concrete. New switches will go in with improved drainage to keep them clear of water and debris that can cause problems during heavy rain storms. On the Morrison side of 11th Avenue, the switches will get heaters to help keep snow and ice from building up, an especially good idea after last winter.

The original cable connecting the train signals to the track will also be replaced, and circuits that help monitor where trains are will be upgraded. These improvements will cut down on signal issues and keep trains moving.

Walking through these intersections today, you have to step carefully around broken and missing brick pavers and historic Portland Belgian block. We’ll replace those. The potholes caused by asphalt crumbling and pulling away from the rails will be repaired using a rubberized grout, which keeps the rail in place and prevents stray current as electricity from the overhead wire travels to the train and into the rail.

Down the street at 1st Avenue, crews will replace curved rail, which wears faster than straight rail. We’ll also be freshening up some signs at the closed platforms and working on our ticket machines.

The Morrison-Yamhill MAX Improvements project has been two years in the making. And since we know the three-week disruption to MAX service (and two-week disruption to Portland Streetcar) is going to be a big inconvenience, we’ve coordinated with other agencies to get all the disruptive work done at once. The Portland Bureau of Environmental Services will repair and upgrade sewers next to the tracks, Multnomah County will fix cracks under the Burnside Bridge and Portland Parks and Recreation will repair material under the Pioneer Square South MAX Station all at the same time our work is happening. We figured an intense three-week disruption is better than months of separate projects that block MAX.

We’re asking a lot from our riders during this project. We appreciate your patience and we can’t wait to debut smoother and more reliable MAX service next month.

Learn more about the Morrison-Yamhill MAX Improvements project
Sarah Touey

Sarah Touey

I’m the resident engineer for TriMet’s Maintenance of Way projects. I seek out adventure by traveling and exploring other transit systems across the country, spending time at the beach with family and friends, and continuously remodeling our house with my husband Jarrett.

More Posts

The Plan For Rose Quarter

From Sunday, August 21, to Saturday, September 3, we’re making improvements near the Rose Quarter to improve MAX reliability and make for a smoother ride.

Much like the work we completed along 1st Avenue in May, we’ll be replacing switches and improving the tracks just east of the Rose Quarter MAX Station. Switches in this area are 30 years old, so crews will replace the wooden ties (which were standard back in 1985) underneath the switches with a concrete track structure and much more durable and robust materials.

We’ll also realign the section of track that runs westbound into the Rose Quarter MAX Station. We’ll begin by removing the rails and that run into the old Trolley Barn. Then, we’ll smooth out the curve into the north platform, which will create a smoother ride into the station. This new design will help eliminate some long-term maintenance challenges and reduce wear and tear on the tracks. As part of the realignment, crews will adjust the overhead wire and relocate two existing poles.

We’ll also be updating the antiquated MAX signal system in the Rose Quarter area. Signal technology has improved dramatically since these were installed back in 1986. This will be the first time in MAX’s history that we’re upgrading the original signals — it’s kind of like rewiring part of your house. We’re most excited for this upgrade because it will decrease the chances of a signal malfunction, which causes train delays.

All of these much-needed renovations are to improve MAX reliability and keep trains running on time, but this work will disrupt regular MAX service for two weeks as we’ll have to shut down service along Holladay Street between the Rose Quarter and the Lloyd Center/NE 11th Ave MAX Station.

We know this two-week disruption will be a hassle, but it’s all for a good cause — to create a better and smoother ride for you.

Learn more about this MAX disruption and how your trips will be affected

Sarah Touey

Sarah Touey

I’m the resident engineer for TriMet’s Maintenance of Way projects. I seek out adventure by traveling and exploring other transit systems across the country, spending time at the beach with family and friends, and continuously remodeling our house with my husband Jarrett.

More Posts